Skip to content

How do I set up a twice-weekly service? ​

Some customers need a visit more than once a week. For example, a busy kitchen might need its mats changed on Monday and Thursday.

A route visits a site on one day of the week. So for two visits a week, the site needs two routes, on different days, with the same items on both. For three visits a week, it needs three routes, and so on.

Adding the second visit ​

  1. Click CRM, then the Site Delivery tab.
  2. Use the Find... box to find the site, and select it.
  3. Click the Routes tab. You'll see the route the site already has.
  4. Click Create Route.
  5. Choose the Route and the second Day, for example Thursday.
  6. Choose the Period. For every week, choose ABCD.
  7. Fill in the Sequence and Duration, then click Save.
  8. Select the new route in the list.
  9. In the NOT ON THIS ROUTE list, on the right, select the items to be serviced on that day.
  10. Click Allocate. You can also drag them to the ON THIS ROUTE list, on the left.

The same items are now on both routes, so they're serviced on both days. For more on creating routes, see Scheduling a Site Delivery.

If the manifests for the coming days are already created, rebuild the new day's route so the visit is added. See How to Create the Manifest.

Updating the agreement ​

Now change each item's Frequency on the agreement, so it shows the right number of visits.

  1. Click CRM, then the Live Agreements tab, and select the agreement.
  2. On the Items tab, select the item and click Edit….
  3. Choose the Frequency that matches the total number of visits.
  4. Check Each Per Year and Each Per Visit, then click Save.

The yearly price doesn't go up by itself when the visits double. If the customer is paying more, change the price. See How do I change how often an item is serviced?

Only some items twice a week ​

If only some items need the extra visit, put only those items on the second route. The rest stay on the first route only.

Going back to once a week ​

  1. On the site's Routes tab, select the extra route.
  2. In the ON THIS ROUTE list, select all the items and click Remove.
  3. Click Delete Route.
  4. Change each item's Frequency back on the agreement, and check the price.

Delete Route is greyed out until every item has been removed from the route.