How do I use Route Admin to manage my routes?
To efficiently manage your scheduled routes, it’s ideal to handle everything from a single location. The best spot for this is the Route Admin tab within the Schedule section. Here, you can add new jobs to a route, modify existing ones, rearrange jobs in the delivery sequence, and even optimise the entire route.
Video Walkthrough
An overview video of the Route Admin tab can be found below:
Adding new jobs
- Click Schedule, then the Route Admin tab.
- Click New on the Overview tab in the bottom half of the screen.
- A window opens for you to choose the site that this job is for. Find it using the Find... box, select it and click Ok.
Enter the following compulsory fields:
- Route – The route that this job is going to be completed on. Once you have selected a site, you can click the Search for nearby sites button to see nearby sites.
- Day – The day on which this job is scheduled to be completed.
- Period – The delivery period during which this job is set to be completed. See Understanding Delivery Periods for more information.
- Sequence – The position of this job in the list of scheduled jobs.
- Duration – The estimated time, in minutes, required to complete this specific job.
Once you have entered all of the details, click Save. Your job will be saved, ready to have items allocated to it. The job will also appear on the Site Delivery tab for the selected site.
Allocating Items
- Click Schedule, then the Route Admin tab.
- Use the Route, Day and Period lists along the top to find your job, and select it.
- Select the Items tab in the bottom half of the screen, followed by the Live Items tab.
TIP
There are two tabs, one for Live Items and one for Pending Items, that is, items on agreements that are still at the Pending Agreement stage. You can allocate items for both in the same manner from the appropriate tab.
The items already on this job are shown on the left, under ON THIS ROUTE. Items not yet on a route are shown on the right, under NOT ON THIS ROUTE.
- In the NOT ON THIS ROUTE list, select the item(s) that you want to allocate. You can select multiple at once.
- Drag them over to the ON THIS ROUTE list on the left. You can also click the Allocate button.
The item(s) will now move from the right to the left.
TIP
To take items off the job, drag them from ON THIS ROUTE back over to NOT ON THIS ROUTE, or select them and click Remove.
Moving jobs up and down in the sequence
- Click Schedule, then the Route Admin tab.
- Use the lists along the top to find the route that your job is on.
TIP
You can only rearrange a job’s sequence using the up and down arrows if you are viewing a single route on a single day. For example, you might choose Route 1 on a Wednesday. If your list includes more than one route or day, you won’t be able to adjust the job sequence.
- Once you have found your job, select it in the list. Then press the up and down arrows on the Overview tab to move it in the sequence.
- You will be asked if you are sure you want to move that job in the sequence. Click Yes.
Optimising a route
Click Options → Optimise Route at the top of the screen. A detailed article specifically for optimising a route can be found on the Understanding Route Optimisation page.